ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC Beet sugar
3+ Characters Required for Products

6

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $1,932k 1,000k
MMBtu
$2.10
- Electrical $309k 8,215k
kWh
$0.038
- Natural Gas $586k 134k
MMBtu
$3.18

35

Recommendations

5.8

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $212k 16k
MMBtu
1.6%
- Electrical $63k 1,527k
kWh
18.6%
- Natural Gas $48k -
MMBtu
-
Waste -
Productivity/Other -
TOTAL $212k
*May be negative reflecting an increased cost component required to save energy and costs overall

6

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $1,932k 1,000k
MMBtu
$2.10
- Electrical $309k 8,215k
kWh
$0.038
- Natural Gas $586k 134k
MMBtu
$3.18

27

Implemented Recommendations

4.5

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $87k 2.2k
MMBtu
0.2%
- Electrical $8.3k 219k
kWh
2.7%
- Natural Gas $1.9k -
MMBtu
-
Waste -
Productivity/Other -
TOTAL $87k
*May be negative reflecting an increased cost component required to save energy and costs overall