ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS 3+ Digits Required
SIC Fluid milk
3+ Characters Required for Products

176

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $810k 121k
MMBtu
$6.74
- Electrical $430k 7,697k
kWh
$0.059
- Natural Gas $212k 38k
MMBtu
$5.03

1,396

Recommendations

7.9

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $87k 8.5k
MMBtu
7.0%
- Electrical $49k 831k
kWh
10.8%
- Natural Gas $26k -
MMBtu
-
Waste $12k
Productivity/Other $53k
TOTAL $153k
*May be negative reflecting an increased cost component required to save energy and costs overall

172

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $788k 120k
MMBtu
$6.55
- Electrical $424k 7,724k
kWh
$0.057
- Natural Gas $201k 37k
MMBtu
$4.95

657

Implemented Recommendations

3.8

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $29k 3.3k
MMBtu
2.7%
- Electrical $18k 319k
kWh
4.1%
- Natural Gas $5.4k -
MMBtu
-
Waste $3.0k
Productivity/Other $30k
TOTAL $62k
*May be negative reflecting an increased cost component required to save energy and costs overall