The ITAC Statistics page displays the average assessment results for the selected criteria.
| ARC | 2+ Digits Required | |
| NAICS | 3+ Digits Required | |
| SIC | Crushed and broken stone, not elsewhere classified | |
| 3+ Characters Required for Products | ||
3
Matching Assessments
| Initial Plant Size Averages | Costs | Usage | Unit Cost | |
|---|---|---|---|---|
| All Energy | $1,993k | 194k |
MMBtu
|
$13.64 |
| - Electrical | $1,071k | 17,472k |
kWh
|
$0.041 |
| - Natural Gas | - | - |
MMBtu
|
- |
16
Recommendations
5.3
Recommendations Per Assessment
| Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
|---|---|---|---|---|
| All Energy | $70k | 3.1k |
MMBtu
|
1.6% |
| - Electrical | $19k | 307k |
kWh
|
1.8% |
| - Natural Gas | - | - |
MMBtu
|
- |
| Waste | - | |||
| Productivity/Other | $303k | |||
| TOTAL | $373k | |||
| *May be negative reflecting an increased cost component required to save energy and costs overall | ||||
2
with Implementation Data
| Initial Plant Size Averages | Costs | Usage | Unit Cost | |
|---|---|---|---|---|
| All Energy | $2,512k | 269k |
MMBtu
|
$9.45 |
| - Electrical | $1,606k | 26,208k |
kWh
|
$0.061 |
| - Natural Gas | - | - |
MMBtu
|
- |
7
Implemented Recommendations
3.5
Implemented Per Assessment
| Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
|---|---|---|---|---|
| All Energy | $36k | 4.3k |
MMBtu
|
1.6% |
| - Electrical | $26k | 416k |
kWh
|
1.6% |
| - Natural Gas | - | - |
MMBtu
|
- |
| Waste | - | |||
| Productivity/Other | $249k | |||
| TOTAL | $285k | |||
| *May be negative reflecting an increased cost component required to save energy and costs overall | ||||