ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS Justice, public order, and safety activities
SIC 2+ Digits Required
3+ Characters Required for Products

4

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $56k 5.2k
MMBtu
$10.72
- Electrical $38k 439k
kWh
$0.096
- Natural Gas $8.6k 0.7k
MMBtu
$12.24

17

Recommendations

4.3

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $12k 1.1k
MMBtu
21.0%
- Electrical $9.2k 107k
kWh
24.4%
- Natural Gas $2.2k -
MMBtu
-
Waste -
Productivity/Other -
TOTAL $12k
*May be negative reflecting an increased cost component required to save energy and costs overall

2

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $65k 6.4k
MMBtu
$9.80
- Electrical $36k 542k
kWh
$0.075
- Natural Gas $9.2k 0.8k
MMBtu
$11.99

4

Implemented Recommendations

2.0

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $3.5k 0.3k
MMBtu
5.1%
- Electrical $1.9k 32k
kWh
5.9%
- Natural Gas $1.5k -
MMBtu
-
Waste -
Productivity/Other -
TOTAL $3.5k