ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS Industrial launderers
SIC 2+ Digits Required
3+ Characters Required for Products

9

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $419k 47k
MMBtu
$9.58
- Electrical $137k 1,531k
kWh
$0.089
- Natural Gas $217k 30k
MMBtu
$8.08

68

Recommendations

7.6

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $105k 7.4k
MMBtu
15.9%
- Electrical $69k 726k
kWh
47.4%
- Natural Gas $22k -
MMBtu
-
Waste $5.1k
Productivity/Other $0.4k
TOTAL $111k
*May be negative reflecting an increased cost component required to save energy and costs overall

7

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $358k 50k
MMBtu
$7.52
- Electrical $146k 1,733k
kWh
$0.079
- Natural Gas $172k 32k
MMBtu
$5.95

16

Implemented Recommendations

2.3

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $1.7k 0.1k
MMBtu
0.2%
- Electrical $1.0k 12k
kWh
0.7%
- Natural Gas $0.3k -
MMBtu
-
Waste $2.1k
Productivity/Other $27k
TOTAL $31k
*May be negative reflecting an increased cost component required to save energy and costs overall