The ITAC Statistics page displays the average assessment results for the selected criteria.
3
Matching Assessments
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $442k | 57k |
MMBtu
|
$9.15 |
- Electrical | $230k | 4,406k |
kWh
|
$0.057 |
- Natural Gas | $65k | 12k |
MMBtu
|
$1.77 |
19
Recommendations
6.3
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $25k | 4.4k |
MMBtu
|
7.6% |
- Electrical | $24k | 425k |
kWh
|
9.6% |
- Natural Gas | $1.0k | - |
MMBtu
|
- |
Waste | - | |||
Productivity/Other | $4.1k | |||
TOTAL | $30k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
3
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $442k | 57k |
MMBtu
|
$9.15 |
- Electrical | $230k | 4,406k |
kWh
|
$0.057 |
- Natural Gas | $65k | 12k |
MMBtu
|
$1.77 |
4
Implemented Recommendations
1.3
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $0.9k | 0.1k |
MMBtu
|
0.2% |
- Electrical | $0.9k | 12k |
kWh
|
0.3% |
- Natural Gas | - | - |
MMBtu
|
- |
Waste | - | |||
Productivity/Other | - | |||
TOTAL | $0.9k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |