ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS Bowling centers
SIC 2+ Digits Required
3+ Characters Required for Products

1

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $143k 14k
MMBtu
$10.01
- Electrical $67k 1,003k
kWh
$0.067
- Natural Gas $22k 4.0k
MMBtu
$5.46

4

Recommendations

4.0

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $12k 1.0k
MMBtu
7.1%
- Electrical $6.6k 99k
kWh
9.8%
- Natural Gas -
-
MMBtu
-
Waste -
Productivity/Other $0.9k
TOTAL $13k
*May be negative reflecting an increased cost component required to save energy and costs overall

0

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy -
-
MMBtu
-
- Electrical -
-
kWh
-
- Natural Gas -
-
MMBtu
-

0

Implemented Recommendations

0.0

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy -
-
MMBtu
-
- Electrical -
-
kWh
-
- Natural Gas -
-
MMBtu
-
Waste -
Productivity/Other -
TOTAL -
*May be negative reflecting an increased cost component required to save energy and costs overall