The ITAC Statistics page displays the average assessment results for the selected criteria.
14
Matching Assessments
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $410k | 50k |
MMBtu
|
$9.70 |
- Electrical | $333k | 4,570k |
kWh
|
$0.077 |
- Natural Gas | $23k | 3.1k |
MMBtu
|
$6.19 |
62
Recommendations
4.4
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $47k | 4.9k |
MMBtu
|
9.9% |
- Electrical | $38k | 483k |
kWh
|
10.6% |
- Natural Gas | $4.9k | - |
MMBtu
|
- |
Waste | - | |||
Productivity/Other | $0.9k | |||
TOTAL | $48k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
7
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $661k | 81k |
MMBtu
|
$10.42 |
- Electrical | $561k | 7,490k |
kWh
|
$0.085 |
- Natural Gas | $26k | 3.7k |
MMBtu
|
$4.92 |
15
Implemented Recommendations
2.1
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $27k | 2.2k |
MMBtu
|
2.8% |
- Electrical | $20k | 217k |
kWh
|
2.9% |
- Natural Gas | $1.3k | - |
MMBtu
|
- |
Waste | - | |||
Productivity/Other | - | |||
TOTAL | $27k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |