The ITAC Statistics page displays the average assessment results for the selected criteria.
13
Matching Assessments
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $220k | 24k |
MMBtu
|
$10.07 |
- Electrical | $138k | 2,136k |
kWh
|
$0.080 |
- Natural Gas | $8.0k | 1.1k |
MMBtu
|
$3.52 |
72
Recommendations
5.5
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $22k | 2.1k |
MMBtu
|
8.8% |
- Electrical | $16k | 209k |
kWh
|
9.8% |
- Natural Gas | $0.1k | - |
MMBtu
|
- |
Waste | - | |||
Productivity/Other | $4.2k | |||
TOTAL | $27k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
10
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $260k | 29k |
MMBtu
|
$9.94 |
- Electrical | $157k | 2,574k |
kWh
|
$0.070 |
- Natural Gas | $7.9k | 1.0k |
MMBtu
|
$3.40 |
23
Implemented Recommendations
2.3
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $12k | 1.5k |
MMBtu
|
5.3% |
- Electrical | $9.5k | 150k |
kWh
|
5.8% |
- Natural Gas | - | - |
MMBtu
|
- |
Waste | - | |||
Productivity/Other | $0.2k | |||
TOTAL | $13k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |