The ITAC Statistics page displays the average assessment results for the selected criteria.
8
Matching Assessments
| Initial Plant Size Averages | Costs | Usage | Unit Cost | |
|---|---|---|---|---|
| All Energy | $130k | 12k |
MMBtu
|
$10.60 |
| - Electrical | $62k | 831k |
kWh
|
$0.094 |
| - Natural Gas | $41k | 3.5k |
MMBtu
|
$7.32 |
38
Recommendations
4.8
Recommendations Per Assessment
| Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
|---|---|---|---|---|
| All Energy | $25k | 2.4k |
MMBtu
|
19.7% |
| - Electrical | $17k | 231k |
kWh
|
27.8% |
| - Natural Gas | $4.8k | - |
MMBtu
|
- |
| Waste | $0.6k | |||
| Productivity/Other | $0.1k | |||
| TOTAL | $25k | |||
| *May be negative reflecting an increased cost component required to save energy and costs overall | ||||
6
with Implementation Data
| Initial Plant Size Averages | Costs | Usage | Unit Cost | |
|---|---|---|---|---|
| All Energy | $147k | 12k |
MMBtu
|
$11.82 |
| - Electrical | $65k | 769k |
kWh
|
$0.11 |
| - Natural Gas | $53k | 4.3k |
MMBtu
|
$8.32 |
15
Implemented Recommendations
2.5
Implemented Per Assessment
| Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
|---|---|---|---|---|
| All Energy | $14k | 1.4k |
MMBtu
|
11.2% |
| - Electrical | $10k | 133k |
kWh
|
17.3% |
| - Natural Gas | $0.5k | - |
MMBtu
|
- |
| Waste | - | |||
| Productivity/Other | ($-0.1)k | |||
| TOTAL | $14k | |||
| *May be negative reflecting an increased cost component required to save energy and costs overall | ||||