The ITAC Statistics page displays the average assessment results for the selected criteria.
2
Matching Assessments
| Initial Plant Size Averages | Costs | Usage | Unit Cost | |
|---|---|---|---|---|
| All Energy | $56k | 4.8k |
MMBtu
|
$11.90 |
| - Electrical | $22k | 223k |
kWh
|
$0.11 |
| - Natural Gas | $4.5k | 2.5k |
MMBtu
|
$1.77 |
13
Recommendations
6.5
Recommendations Per Assessment
| Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
|---|---|---|---|---|
| All Energy | $52k | 3.3k |
MMBtu
|
70.0% |
| - Electrical | $42k | 326k |
kWh
|
146.5% |
| - Natural Gas | - | - |
MMBtu
|
- |
| Waste | - | |||
| Productivity/Other | - | |||
| TOTAL | $52k | |||
| *May be negative reflecting an increased cost component required to save energy and costs overall | ||||
0
with Implementation Data
| Initial Plant Size Averages | Costs | Usage | Unit Cost | |
|---|---|---|---|---|
| All Energy | - | - |
MMBtu
|
- |
| - Electrical | - | - |
kWh
|
- |
| - Natural Gas | - | - |
MMBtu
|
- |
0
Implemented Recommendations
0.0
Implemented Per Assessment
| Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
|---|---|---|---|---|
| All Energy | - | - |
MMBtu
|
- |
| - Electrical | - | - |
kWh
|
- |
| - Natural Gas | - | - |
MMBtu
|
- |
| Waste | - | |||
| Productivity/Other | - | |||
| TOTAL | - | |||
| *May be negative reflecting an increased cost component required to save energy and costs overall | ||||