The ITAC Statistics page displays the average assessment results for the selected criteria.
1
Matching Assessments
| Initial Plant Size Averages | Costs | Usage | Unit Cost | |
|---|---|---|---|---|
| All Energy | $201k | 11k |
MMBtu
|
$18.21 |
| - Electrical | $125k | 994k |
kWh
|
$0.13 |
| - Natural Gas | - | - |
MMBtu
|
- |
7
Recommendations
7.0
Recommendations Per Assessment
| Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
|---|---|---|---|---|
| All Energy | $9.5k | 0.5k |
MMBtu
|
4.1% |
| - Electrical | $5.6k | 45k |
kWh
|
4.5% |
| - Natural Gas | - | - |
MMBtu
|
- |
| Waste | - | |||
| Productivity/Other | $0.7k | |||
| TOTAL | $10k | |||
| *May be negative reflecting an increased cost component required to save energy and costs overall | ||||
0
with Implementation Data
| Initial Plant Size Averages | Costs | Usage | Unit Cost | |
|---|---|---|---|---|
| All Energy | - | - |
MMBtu
|
- |
| - Electrical | - | - |
kWh
|
- |
| - Natural Gas | - | - |
MMBtu
|
- |
0
Implemented Recommendations
0.0
Implemented Per Assessment
| Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
|---|---|---|---|---|
| All Energy | - | - |
MMBtu
|
- |
| - Electrical | - | - |
kWh
|
- |
| - Natural Gas | - | - |
MMBtu
|
- |
| Waste | - | |||
| Productivity/Other | - | |||
| TOTAL | - | |||
| *May be negative reflecting an increased cost component required to save energy and costs overall | ||||