ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS Elementary and secondary schools
SIC 2+ Digits Required
3+ Characters Required for Products

94

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $137k 12k
MMBtu
$11.83
- Electrical $89k 1,033k
kWh
$0.088
- Natural Gas $15k 1.8k
MMBtu
$6.72

491

Recommendations

5.2

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $44k 4.0k
MMBtu
31.9%
- Electrical $35k 389k
kWh
37.7%
- Natural Gas $1.5k -
MMBtu
-
Waste $1.2k
Productivity/Other $1.4k
TOTAL $47k
*May be negative reflecting an increased cost component required to save energy and costs overall

46

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $159k 16k
MMBtu
$11.33
- Electrical $114k 1,269k
kWh
$0.099
- Natural Gas $18k 2.5k
MMBtu
$3.91

135

Implemented Recommendations

2.9

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $19k 1.8k
MMBtu
11.3%
- Electrical $16k 174k
kWh
13.7%
- Natural Gas $0.7k -
MMBtu
-
Waste $0.0k
Productivity/Other $0.2k
TOTAL $19k
*May be negative reflecting an increased cost component required to save energy and costs overall