The ITAC Statistics page displays the average assessment results for the selected criteria.
122
Matching Assessments
| Initial Plant Size Averages | Costs | Usage | Unit Cost | |
|---|---|---|---|---|
| All Energy | $145k | 16k |
MMBtu
|
$10.71 |
| - Electrical | $83k | 1,091k |
kWh
|
$0.085 |
| - Natural Gas | $24k | 4.0k |
MMBtu
|
$6.50 |
636
Recommendations
5.2
Recommendations Per Assessment
| Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
|---|---|---|---|---|
| All Energy | $36k | 3.3k |
MMBtu
|
20.4% |
| - Electrical | $26k | 322k |
kWh
|
29.5% |
| - Natural Gas | $3.1k | - |
MMBtu
|
- |
| Waste | $0.3k | |||
| Productivity/Other | $2.5k | |||
| TOTAL | $39k | |||
| *May be negative reflecting an increased cost component required to save energy and costs overall | ||||
64
with Implementation Data
| Initial Plant Size Averages | Costs | Usage | Unit Cost | |
|---|---|---|---|---|
| All Energy | $173k | 21k |
MMBtu
|
$10.00 |
| - Electrical | $99k | 1,318k |
kWh
|
$0.084 |
| - Natural Gas | $34k | 6.1k |
MMBtu
|
$4.85 |
166
Implemented Recommendations
2.6
Implemented Per Assessment
| Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
|---|---|---|---|---|
| All Energy | $19k | 1.5k |
MMBtu
|
7.2% |
| - Electrical | $12k | 148k |
kWh
|
11.2% |
| - Natural Gas | $1.6k | - |
MMBtu
|
- |
| Waste | $0.4k | |||
| Productivity/Other | $2.7k | |||
| TOTAL | $22k | |||
| *May be negative reflecting an increased cost component required to save energy and costs overall | ||||