The ITAC Statistics page displays the average assessment results for the selected criteria.
113
Matching Assessments
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $146k | 16k |
MMBtu
|
$10.60 |
- Electrical | $83k | 1,100k |
kWh
|
$0.084 |
- Natural Gas | $25k | 4.2k |
MMBtu
|
$6.30 |
592
Recommendations
5.2
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $37k | 3.5k |
MMBtu
|
21.0% |
- Electrical | $27k | 338k |
kWh
|
30.7% |
- Natural Gas | $3.3k | - |
MMBtu
|
- |
Waste | $0.3k | |||
Productivity/Other | $2.6k | |||
TOTAL | $40k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
63
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $173k | 21k |
MMBtu
|
$10.05 |
- Electrical | $100k | 1,327k |
kWh
|
$0.085 |
- Natural Gas | $33k | 5.7k |
MMBtu
|
$4.85 |
156
Implemented Recommendations
2.5
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $19k | 1.5k |
MMBtu
|
7.2% |
- Electrical | $12k | 147k |
kWh
|
11.1% |
- Natural Gas | $1.6k | - |
MMBtu
|
- |
Waste | $0.4k | |||
Productivity/Other | $2.7k | |||
TOTAL | $22k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |