The ITAC Statistics page displays the average assessment results for the selected criteria.
5
Matching Assessments
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $81k | 8.8k |
MMBtu
|
$11.48 |
- Electrical | $40k | 737k |
kWh
|
$0.089 |
- Natural Gas | $12k | 1.2k |
MMBtu
|
$12.37 |
31
Recommendations
6.2
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $30k | 2.5k |
MMBtu
|
27.9% |
- Electrical | $18k | 239k |
kWh
|
32.5% |
- Natural Gas | $2.6k | - |
MMBtu
|
- |
Waste | $1.6k | |||
Productivity/Other | $1.1k | |||
TOTAL | $32k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
3
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $122k | 13k |
MMBtu
|
$12.17 |
- Electrical | $58k | 1,147k |
kWh
|
$0.070 |
- Natural Gas | $16k | 1.6k |
MMBtu
|
$14.09 |
9
Implemented Recommendations
3.0
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $26k | 2.1k |
MMBtu
|
15.7% |
- Electrical | $8.8k | 205k |
kWh
|
17.9% |
- Natural Gas | $2.2k | - |
MMBtu
|
- |
Waste | $2.6k | |||
Productivity/Other | - | |||
TOTAL | $28k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |