15
Matching Assessments
| Initial Plant Size Averages | Costs | Usage | Unit Cost | |
|---|---|---|---|---|
| All Energy | $114k | 9.4k |
MMBtu
|
$14.41 |
| - Electrical | $75k | 803k |
kWh
|
$0.12 |
| - Natural Gas | $12k | 1.2k |
MMBtu
|
$8.45 |
77
Recommendations
5.1
Recommendations Per Assessment
| Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
|---|---|---|---|---|
| All Energy | $35k | 2.0k |
MMBtu
|
21.6% |
| - Electrical | $25k | 199k |
kWh
|
24.8% |
| - Natural Gas | $4.3k | - |
MMBtu
|
- |
| Waste | $0.6k | |||
| Productivity/Other | $0.5k | |||
| TOTAL | $36k | |||
| *May be negative reflecting an increased cost component required to save energy and costs overall | ||||
8
with Implementation Data
| Initial Plant Size Averages | Costs | Usage | Unit Cost | |
|---|---|---|---|---|
| All Energy | $76k | 7.6k |
MMBtu
|
$11.68 |
| - Electrical | $37k | 564k |
kWh
|
$0.099 |
| - Natural Gas | $18k | 1.8k |
MMBtu
|
$10.30 |
17
Implemented Recommendations
2.1
Implemented Per Assessment
| Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
|---|---|---|---|---|
| All Energy | $14k | 0.9k |
MMBtu
|
11.3% |
| - Electrical | $4.1k | 84k |
kWh
|
14.9% |
| - Natural Gas | $4.6k | - |
MMBtu
|
- |
| Waste | $1.0k | |||
| Productivity/Other | $0.1k | |||
| TOTAL | $15k | |||
| *May be negative reflecting an increased cost component required to save energy and costs overall | ||||