The ITAC Statistics page displays the average assessment results for the selected criteria.
18
Matching Assessments
| Initial Plant Size Averages | Costs | Usage | Unit Cost | |
|---|---|---|---|---|
| All Energy | $270k | 34k |
MMBtu
|
$10.55 |
| - Electrical | $149k | 2,254k |
kWh
|
$0.094 |
| - Natural Gas | $52k | 11k |
MMBtu
|
$5.67 |
106
Recommendations
5.9
Recommendations Per Assessment
| Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
|---|---|---|---|---|
| All Energy | $58k | 4.5k |
MMBtu
|
13.2% |
| - Electrical | $32k | 441k |
kWh
|
19.6% |
| - Natural Gas | $12k | - |
MMBtu
|
- |
| Waste | - | |||
| Productivity/Other | $6.5k | |||
| TOTAL | $64k | |||
| *May be negative reflecting an increased cost component required to save energy and costs overall | ||||
14
with Implementation Data
| Initial Plant Size Averages | Costs | Usage | Unit Cost | |
|---|---|---|---|---|
| All Energy | $288k | 40k |
MMBtu
|
$8.80 |
| - Electrical | $163k | 2,667k |
kWh
|
$0.084 |
| - Natural Gas | $49k | 12k |
MMBtu
|
$4.68 |
44
Implemented Recommendations
3.1
Implemented Per Assessment
| Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
|---|---|---|---|---|
| All Energy | $29k | 3.5k |
MMBtu
|
8.7% |
| - Electrical | $19k | 339k |
kWh
|
12.7% |
| - Natural Gas | $4.0k | - |
MMBtu
|
- |
| Waste | - | |||
| Productivity/Other | $3.1k | |||
| TOTAL | $32k | |||
| *May be negative reflecting an increased cost component required to save energy and costs overall | ||||