The ITAC Statistics page displays the average assessment results for the selected criteria.
33
Matching Assessments
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $640k | 67k |
MMBtu
|
$11.29 |
- Electrical | $357k | 4,493k |
kWh
|
$0.088 |
- Natural Gas | $125k | 20k |
MMBtu
|
$4.02 |
208
Recommendations
6.3
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $112k | 8.0k |
MMBtu
|
12.1% |
- Electrical | $71k | 785k |
kWh
|
17.5% |
- Natural Gas | $20k | - |
MMBtu
|
- |
Waste | $0.2k | |||
Productivity/Other | $23k | |||
TOTAL | $135k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
23
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $448k | 60k |
MMBtu
|
$9.50 |
- Electrical | $184k | 3,101k |
kWh
|
$0.075 |
- Natural Gas | $171k | 28k |
MMBtu
|
$3.22 |
76
Implemented Recommendations
3.3
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $27k | 3.1k |
MMBtu
|
5.1% |
- Electrical | $19k | 300k |
kWh
|
9.7% |
- Natural Gas | $1.9k | - |
MMBtu
|
- |
Waste | - | |||
Productivity/Other | $14k | |||
TOTAL | $41k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |