The ITAC Statistics page displays the average assessment results for the selected criteria.
1
Matching Assessments
| Initial Plant Size Averages | Costs | Usage | Unit Cost | |
|---|---|---|---|---|
| All Energy | $501k | 88k |
MMBtu
|
$5.71 |
| - Electrical | $121k | 1,541k |
kWh
|
$0.078 |
| - Natural Gas | $357k | 72k |
MMBtu
|
$4.96 |
9
Recommendations
9.0
Recommendations Per Assessment
| Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
|---|---|---|---|---|
| All Energy | $368k | 12k |
MMBtu
|
14.2% |
| - Electrical | $95k | 1,216k |
kWh
|
78.9% |
| - Natural Gas | $270k | - |
MMBtu
|
- |
| Waste | - | |||
| Productivity/Other | $5.1k | |||
| TOTAL | $373k | |||
| *May be negative reflecting an increased cost component required to save energy and costs overall | ||||
1
with Implementation Data
| Initial Plant Size Averages | Costs | Usage | Unit Cost | |
|---|---|---|---|---|
| All Energy | $501k | 88k |
MMBtu
|
$5.71 |
| - Electrical | $121k | 1,541k |
kWh
|
$0.078 |
| - Natural Gas | $357k | 72k |
MMBtu
|
$4.96 |
8
Implemented Recommendations
8.0
Implemented Per Assessment
| Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
|---|---|---|---|---|
| All Energy | $368k | 12k |
MMBtu
|
14.2% |
| - Electrical | $95k | 1,216k |
kWh
|
78.9% |
| - Natural Gas | $270k | - |
MMBtu
|
- |
| Waste | - | |||
| Productivity/Other | $1.5k | |||
| TOTAL | $370k | |||
| *May be negative reflecting an increased cost component required to save energy and costs overall | ||||