The ITAC Statistics page displays the average assessment results for the selected criteria.
4
Matching Assessments
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $985k | 150k |
MMBtu
|
$6.72 |
- Electrical | $495k | 8,204k |
kWh
|
$0.055 |
- Natural Gas | $420k | 66k |
MMBtu
|
$6.19 |
40
Recommendations
10.0
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $205k | 12k |
MMBtu
|
8.0% |
- Electrical | $72k | 1,176k |
kWh
|
14.3% |
- Natural Gas | $127k | - |
MMBtu
|
- |
Waste | $1.8k | |||
Productivity/Other | $18k | |||
TOTAL | $225k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
2
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $1,776k | 273k |
MMBtu
|
$6.51 |
- Electrical | $897k | 14,729k |
kWh
|
$0.056 |
- Natural Gas | $777k | 122k |
MMBtu
|
$6.28 |
13
Implemented Recommendations
6.5
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $241k | 8.3k |
MMBtu
|
3.0% |
- Electrical | $52k | 805k |
kWh
|
5.5% |
- Natural Gas | $185k | - |
MMBtu
|
- |
Waste | - | |||
Productivity/Other | ($-4.6)k | |||
TOTAL | $236k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |