The ITAC Statistics page displays the average assessment results for the selected criteria.
2
Matching Assessments
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $393k | 45k |
MMBtu
|
$9.04 |
- Electrical | $238k | 3,072k |
kWh
|
$0.082 |
- Natural Gas | $133k | 13k |
MMBtu
|
$9.85 |
9
Recommendations
4.5
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $7.1k | 0.2k |
MMBtu
|
0.5% |
- Electrical | $1.3k | 21k |
kWh
|
0.7% |
- Natural Gas | $5.8k | - |
MMBtu
|
- |
Waste | $26k | |||
Productivity/Other | $0.2k | |||
TOTAL | $33k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
2
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $393k | 45k |
MMBtu
|
$9.04 |
- Electrical | $238k | 3,072k |
kWh
|
$0.082 |
- Natural Gas | $133k | 13k |
MMBtu
|
$9.85 |
4
Implemented Recommendations
2.0
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $1.3k | 0.0k |
MMBtu
|
0.0% |
- Electrical | $0.4k | 1.4k |
kWh
|
0.0% |
- Natural Gas | $0.9k | - |
MMBtu
|
- |
Waste | - | |||
Productivity/Other | $0.2k | |||
TOTAL | $1.6k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |