The ITAC Statistics page displays the average assessment results for the selected criteria.
1
Matching Assessments
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $396k | 27k |
MMBtu
|
$14.65 |
- Electrical | $89k | 1,876k |
kWh
|
$0.048 |
- Natural Gas | $86k | 7.8k |
MMBtu
|
$11.10 |
8
Recommendations
8.0
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $186k | 15k |
MMBtu
|
54.4% |
- Electrical | $69k | 1,434k |
kWh
|
76.4% |
- Natural Gas | $43k | - |
MMBtu
|
- |
Waste | - | |||
Productivity/Other | - | |||
TOTAL | $186k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
1
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $396k | 27k |
MMBtu
|
$14.65 |
- Electrical | $89k | 1,876k |
kWh
|
$0.048 |
- Natural Gas | $86k | 7.8k |
MMBtu
|
$11.10 |
1
Implemented Recommendations
1.0
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $1.2k | 0.1k |
MMBtu
|
0.3% |
- Electrical | $0.4k | 7.8k |
kWh
|
0.4% |
- Natural Gas | - | - |
MMBtu
|
- |
Waste | - | |||
Productivity/Other | - | |||
TOTAL | $1.2k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |