ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS Lumber and other construction materials merchant wholesalers
SIC 2+ Digits Required
3+ Characters Required for Products

4

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $408k 54k
MMBtu
$10.76
- Electrical $163k 4,179k
kWh
$0.052
- Natural Gas $54k 7.1k
MMBtu
$4.88

31

Recommendations

7.8

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $101k 8.6k
MMBtu
15.9%
- Electrical $32k 835k
kWh
20.0%
- Natural Gas $19k -
MMBtu
-
Waste -
Productivity/Other $12k
TOTAL $113k
*May be negative reflecting an increased cost component required to save energy and costs overall

3

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $367k 64k
MMBtu
$7.16
- Electrical $198k 5,319k
kWh
$0.043
- Natural Gas $69k 9.3k
MMBtu
$2.48

13

Implemented Recommendations

4.3

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $40k 6.0k
MMBtu
9.4%
- Electrical $20k 582k
kWh
10.9%
- Natural Gas -
-
MMBtu
-
Waste -
Productivity/Other $16k
TOTAL $56k
*May be negative reflecting an increased cost component required to save energy and costs overall