ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS Merchant wholesalers, durable goods
SIC 2+ Digits Required
3+ Characters Required for Products

35

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $601k 112k
MMBtu
$10.55
- Electrical $330k 5,689k
kWh
$0.084
- Natural Gas $127k 53k
MMBtu
$6.93

265

Recommendations

7.6

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $78k 9.4k
MMBtu
8.4%
- Electrical $51k 913k
kWh
16.0%
- Natural Gas $10k -
MMBtu
-
Waste $2.3k
Productivity/Other $13k
TOTAL $93k
*May be negative reflecting an increased cost component required to save energy and costs overall

31

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $627k 120k
MMBtu
$9.92
- Electrical $341k 5,914k
kWh
$0.080
- Natural Gas $139k 59k
MMBtu
$6.99

117

Implemented Recommendations

3.8

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $28k 3.6k
MMBtu
3.0%
- Electrical $16k 353k
kWh
6.0%
- Natural Gas $4.0k -
MMBtu
-
Waste $1.0k
Productivity/Other $8.7k
TOTAL $37k
*May be negative reflecting an increased cost component required to save energy and costs overall