ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS Other miscellaneous manufacturing
SIC 2+ Digits Required
3+ Characters Required for Products

186

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $814k 119k
MMBtu
$9.51
- Electrical $422k 7,510k
kWh
$0.075
- Natural Gas $218k 41k
MMBtu
$6.42

1,447

Recommendations

7.8

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $117k 13k
MMBtu
10.9%
- Electrical $71k 1,262k
kWh
16.8%
- Natural Gas $13k -
MMBtu
-
Waste $1.9k
Productivity/Other $26k
TOTAL $145k
*May be negative reflecting an increased cost component required to save energy and costs overall

178

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $821k 121k
MMBtu
$9.41
- Electrical $425k 7,656k
kWh
$0.074
- Natural Gas $221k 42k
MMBtu
$6.31

613

Implemented Recommendations

3.4

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $28k 2.5k
MMBtu
2.1%
- Electrical $15k 244k
kWh
3.2%
- Natural Gas $6.8k -
MMBtu
-
Waste $0.7k
Productivity/Other $5.6k
TOTAL $34k
*May be negative reflecting an increased cost component required to save energy and costs overall