ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
NAICS 337211 Wood office furniture manufacturing

19

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $587k 79k
MMBtu
$8.60
- Electrical $356k 5,622k
kWh
$0.070
- Natural Gas $123k 19k
MMBtu
$6.40

133

Recommendations

7.0

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $98k 6.9k
MMBtu
8.7%
- Electrical $53k 669k
kWh
11.9%
- Natural Gas $22k -
MMBtu
-
Waste $2.1k
Productivity/Other $11k
TOTAL $111k
*May be negative reflecting an increased cost component required to save energy and costs overall

18

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $610k 82k
MMBtu
$8.62
- Electrical $370k 5,848k
kWh
$0.070
- Natural Gas $127k 20k
MMBtu
$6.31

73

Implemented Recommendations

4.1

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $36k 3.3k
MMBtu
4.1%
- Electrical $27k 324k
kWh
5.5%
- Natural Gas $2.2k -
MMBtu
-
Waste $0.6k
Productivity/Other $11k
TOTAL $48k
*May be negative reflecting an increased cost component required to save energy and costs overall