The ITAC Statistics page displays the average assessment results for the selected criteria.
35
Matching Assessments
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $498k | 74k |
MMBtu
|
$9.29 |
- Electrical | $298k | 4,707k |
kWh
|
$0.062 |
- Natural Gas | $62k | 8.4k |
MMBtu
|
$6.16 |
274
Recommendations
7.8
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $82k | 7.4k |
MMBtu
|
10.0% |
- Electrical | $51k | 724k |
kWh
|
15.4% |
- Natural Gas | $6.0k | - |
MMBtu
|
- |
Waste | $3.1k | |||
Productivity/Other | $17k | |||
TOTAL | $102k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
32
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $518k | 78k |
MMBtu
|
$9.21 |
- Electrical | $315k | 4,918k |
kWh
|
$0.064 |
- Natural Gas | $65k | 8.8k |
MMBtu
|
$5.81 |
125
Implemented Recommendations
3.9
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $30k | 2.6k |
MMBtu
|
3.3% |
- Electrical | $17k | 250k |
kWh
|
5.1% |
- Natural Gas | $2.8k | - |
MMBtu
|
- |
Waste | $0.4k | |||
Productivity/Other | $6.9k | |||
TOTAL | $37k | |||