The ITAC Statistics page displays the average assessment results for the selected criteria.
24
Matching Assessments
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $1,211k | 177k |
MMBtu
|
$9.03 |
- Electrical | $668k | 11,479k |
kWh
|
$0.070 |
- Natural Gas | $231k | 31k |
MMBtu
|
$8.08 |
176
Recommendations
7.3
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $241k | 13k |
MMBtu
|
7.5% |
- Electrical | $70k | 1,288k |
kWh
|
11.2% |
- Natural Gas | $5.2k | - |
MMBtu
|
- |
Waste | $2.0k | |||
Productivity/Other | $23k | |||
TOTAL | $266k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
21
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $1,276k | 192k |
MMBtu
|
$8.89 |
- Electrical | $676k | 12,388k |
kWh
|
$0.066 |
- Natural Gas | $245k | 33k |
MMBtu
|
$7.45 |
73
Implemented Recommendations
3.5
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $139k | 7.7k |
MMBtu
|
4.0% |
- Electrical | $37k | 755k |
kWh
|
6.1% |
- Natural Gas | ($-2.2)k | - |
MMBtu
|
- |
Waste | $1.5k | |||
Productivity/Other | $11k | |||
TOTAL | $151k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |