The ITAC Statistics page displays the average assessment results for the selected criteria.
| ARC | 2+ Digits Required | |
| NAICS | Ship building and repairing | |
| SIC | 2+ Digits Required | |
| 3+ Characters Required for Products | ||
27
Matching Assessments
| Initial Plant Size Averages | Costs | Usage | Unit Cost | |
|---|---|---|---|---|
| All Energy | $462k | 49k |
MMBtu
|
$10.86 |
| - Electrical | $412k | 4,779k |
kWh
|
$0.093 |
| - Natural Gas | $2.8k | 0.3k |
MMBtu
|
$2.33 |
182
Recommendations
6.7
Recommendations Per Assessment
| Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
|---|---|---|---|---|
| All Energy | $105k | 12k |
MMBtu
|
23.3% |
| - Electrical | $93k | 1,123k |
kWh
|
23.5% |
| - Natural Gas | $0.3k | - |
MMBtu
|
- |
| Waste | - | |||
| Productivity/Other | $7.3k | |||
| TOTAL | $112k | |||
| *May be negative reflecting an increased cost component required to save energy and costs overall | ||||
24
with Implementation Data
| Initial Plant Size Averages | Costs | Usage | Unit Cost | |
|---|---|---|---|---|
| All Energy | $472k | 53k |
MMBtu
|
$8.86 |
| - Electrical | $427k | 5,159k |
kWh
|
$0.080 |
| - Natural Gas | $3.1k | 0.3k |
MMBtu
|
$1.90 |
85
Implemented Recommendations
3.5
Implemented Per Assessment
| Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
|---|---|---|---|---|
| All Energy | $55k | 7.3k |
MMBtu
|
13.7% |
| - Electrical | $53k | 711k |
kWh
|
13.8% |
| - Natural Gas | $0.1k | - |
MMBtu
|
- |
| Waste | - | |||
| Productivity/Other | $1.9k | |||
| TOTAL | $56k | |||
| *May be negative reflecting an increased cost component required to save energy and costs overall | ||||