ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS Motor vehicle manufacturing
SIC 2+ Digits Required
3+ Characters Required for Products

42

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $2,568k 413k
MMBtu
$8.44
- Electrical $1,745k 30,303k
kWh
$0.062
- Natural Gas $566k 102k
MMBtu
$6.66

358

Recommendations

8.5

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $226k 25k
MMBtu
6.2%
- Electrical $159k 2,484k
kWh
8.2%
- Natural Gas $51k -
MMBtu
-
Waste $2.2k
Productivity/Other $10k
TOTAL $238k
*May be negative reflecting an increased cost component required to save energy and costs overall

39

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $2,696k 438k
MMBtu
$8.38
- Electrical $1,823k 31,966k
kWh
$0.061
- Natural Gas $604k 109k
MMBtu
$6.52

153

Implemented Recommendations

3.9

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $54k 6.7k
MMBtu
1.5%
- Electrical $35k 651k
kWh
2.0%
- Natural Gas $10k -
MMBtu
-
Waste $0.9k
Productivity/Other $7.0k
TOTAL $61k
*May be negative reflecting an increased cost component required to save energy and costs overall