The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC | 2+ Digits Required | |
NAICS | Current-carrying wiring device manufacturing | |
SIC | 2+ Digits Required | |
3+ Characters Required for Products |
34
Matching Assessments
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $504k | 69k |
MMBtu
|
$8.81 |
- Electrical | $284k | 5,136k |
kWh
|
$0.065 |
- Natural Gas | $89k | 16k |
MMBtu
|
$5.76 |
251
Recommendations
7.4
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $59k | 7.0k |
MMBtu
|
10.1% |
- Electrical | $45k | 678k |
kWh
|
13.2% |
- Natural Gas | $5.7k | - |
MMBtu
|
- |
Waste | $0.7k | |||
Productivity/Other | $39k | |||
TOTAL | $99k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
32
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $514k | 71k |
MMBtu
|
$8.74 |
- Electrical | $288k | 5,230k |
kWh
|
$0.065 |
- Natural Gas | $93k | 17k |
MMBtu
|
$5.53 |
108
Implemented Recommendations
3.4
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $21k | 2.2k |
MMBtu
|
3.1% |
- Electrical | $16k | 213k |
kWh
|
4.1% |
- Natural Gas | $1.5k | - |
MMBtu
|
- |
Waste | - | |||
Productivity/Other | $21k | |||
TOTAL | $42k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |