ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS Fiber optic cable manufacturing
SIC 2+ Digits Required
3+ Characters Required for Products

7

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $642k 100k
MMBtu
$7.86
- Electrical $406k 9,308k
kWh
$0.056
- Natural Gas $39k 4.4k
MMBtu
$6.02

56

Recommendations

8.0

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $110k 15k
MMBtu
14.9%
- Electrical $72k 1,454k
kWh
15.6%
- Natural Gas $3.2k -
MMBtu
-
Waste -
Productivity/Other $30k
TOTAL $141k
*May be negative reflecting an increased cost component required to save energy and costs overall

7

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $642k 100k
MMBtu
$7.86
- Electrical $406k 9,308k
kWh
$0.056
- Natural Gas $39k 4.4k
MMBtu
$6.02

19

Implemented Recommendations

2.7

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $42k 2.7k
MMBtu
2.7%
- Electrical $20k 259k
kWh
2.8%
- Natural Gas $0.3k -
MMBtu
-
Waste -
Productivity/Other $22k
TOTAL $64k
*May be negative reflecting an increased cost component required to save energy and costs overall