ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS Motor and generator manufacturing
SIC 2+ Digits Required
3+ Characters Required for Products

31

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $600k 78k
MMBtu
$8.74
- Electrical $342k 5,578k
kWh
$0.066
- Natural Gas $137k 21k
MMBtu
$8.30

237

Recommendations

7.6

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $68k 6.9k
MMBtu
8.8%
- Electrical $44k 670k
kWh
12.0%
- Natural Gas $5.3k -
MMBtu
-
Waste $0.1k
Productivity/Other $4.2k
TOTAL $73k
*May be negative reflecting an increased cost component required to save energy and costs overall

26

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $635k 84k
MMBtu
$8.46
- Electrical $366k 6,063k
kWh
$0.064
- Natural Gas $148k 22k
MMBtu
$8.24

94

Implemented Recommendations

3.6

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $22k 2.5k
MMBtu
2.9%
- Electrical $16k 239k
kWh
3.9%
- Natural Gas $2.6k -
MMBtu
-
Waste -
Productivity/Other $0.5k
TOTAL $22k
*May be negative reflecting an increased cost component required to save energy and costs overall