ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS Motor and generator manufacturing
SIC 2+ Digits Required
3+ Characters Required for Products

32

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $648k 82k
MMBtu
$8.80
- Electrical $376k 5,805k
kWh
$0.067
- Natural Gas $141k 22k
MMBtu
$8.16

246

Recommendations

7.7

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $89k 8.6k
MMBtu
10.5%
- Electrical $64k 840k
kWh
14.5%
- Natural Gas $5.1k -
MMBtu
-
Waste $0.1k
Productivity/Other $4.1k
TOTAL $93k
*May be negative reflecting an increased cost component required to save energy and costs overall

27

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $620k 82k
MMBtu
$8.53
- Electrical $356k 5,902k
kWh
$0.064
- Natural Gas $144k 21k
MMBtu
$8.37

94

Implemented Recommendations

3.5

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $21k 2.4k
MMBtu
2.9%
- Electrical $16k 231k
kWh
3.9%
- Natural Gas $2.5k -
MMBtu
-
Waste -
Productivity/Other $0.5k
TOTAL $22k
*May be negative reflecting an increased cost component required to save energy and costs overall