ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS Power, distribution, and specialty transformer manufacturing
SIC 2+ Digits Required
3+ Characters Required for Products

26

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $654k 96k
MMBtu
$8.54
- Electrical $333k 6,591k
kWh
$0.060
- Natural Gas $152k 19k
MMBtu
$7.73

189

Recommendations

7.3

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $97k 0.6k
MMBtu
0.6%
- Electrical $35k 57k
kWh
0.9%
- Natural Gas $24k -
MMBtu
-
Waste $5.1k
Productivity/Other $14k
TOTAL $117k
*May be negative reflecting an increased cost component required to save energy and costs overall

26

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $654k 96k
MMBtu
$8.54
- Electrical $333k 6,591k
kWh
$0.060
- Natural Gas $152k 19k
MMBtu
$7.73

88

Implemented Recommendations

3.4

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $38k (-2.2)k
MMBtu
(-2.2)%
- Electrical $14k (-210.6)k
kWh
(-3.2)%
- Natural Gas $13k -
MMBtu
-
Waste $1.1k
Productivity/Other $9.1k
TOTAL $48k
*May be negative reflecting an increased cost component required to save energy and costs overall