The ITAC Statistics page displays the average assessment results for the selected criteria.
6
Matching Assessments
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $615k | 79k |
MMBtu
|
$8.77 |
- Electrical | $375k | 6,834k |
kWh
|
$0.064 |
- Natural Gas | $66k | 8.7k |
MMBtu
|
$5.85 |
44
Recommendations
7.3
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $42k | 4.2k |
MMBtu
|
5.3% |
- Electrical | $26k | 406k |
kWh
|
5.9% |
- Natural Gas | $4.4k | - |
MMBtu
|
- |
Waste | $0.7k | |||
Productivity/Other | $7.6k | |||
TOTAL | $50k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
6
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $615k | 79k |
MMBtu
|
$8.77 |
- Electrical | $375k | 6,834k |
kWh
|
$0.064 |
- Natural Gas | $66k | 8.7k |
MMBtu
|
$5.85 |
17
Implemented Recommendations
2.8
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $14k | 1.5k |
MMBtu
|
2.0% |
- Electrical | $8.9k | 150k |
kWh
|
2.2% |
- Natural Gas | $0.0k | - |
MMBtu
|
- |
Waste | - | |||
Productivity/Other | $5.8k | |||
TOTAL | $20k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |