The ITAC Statistics page displays the average assessment results for the selected criteria.
1
Matching Assessments
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $1,059k | 213k |
MMBtu
|
$4.98 |
- Electrical | $399k | 18,754k |
kWh
|
$0.021 |
- Natural Gas | $188k | 20k |
MMBtu
|
$9.23 |
9
Recommendations
9.0
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $111k | 22k |
MMBtu
|
10.5% |
- Electrical | $60k | 2,227k |
kWh
|
11.9% |
- Natural Gas | $30k | - |
MMBtu
|
- |
Waste | - | |||
Productivity/Other | $33k | |||
TOTAL | $145k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
1
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $1,059k | 213k |
MMBtu
|
$4.98 |
- Electrical | $399k | 18,754k |
kWh
|
$0.021 |
- Natural Gas | $188k | 20k |
MMBtu
|
$9.23 |
7
Implemented Recommendations
7.0
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $76k | 12k |
MMBtu
|
5.5% |
- Electrical | $31k | 1,194k |
kWh
|
6.4% |
- Natural Gas | $30k | - |
MMBtu
|
- |
Waste | - | |||
Productivity/Other | $33k | |||
TOTAL | $109k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |