ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS Semiconductor and other electronic component manufacturing
SIC 2+ Digits Required
3+ Characters Required for Products

227

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $757k 146k
MMBtu
$10.27
- Electrical $517k 8,789k
kWh
$0.079
- Natural Gas $79k 11k
MMBtu
$7.24

1,702

Recommendations

7.5

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $105k 11k
MMBtu
7.4%
- Electrical $76k 1,047k
kWh
11.9%
- Natural Gas $9.5k -
MMBtu
-
Waste $2.2k
Productivity/Other $43k
TOTAL $150k
*May be negative reflecting an increased cost component required to save energy and costs overall

209

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $778k 153k
MMBtu
$10.25
- Electrical $529k 9,088k
kWh
$0.077
- Natural Gas $82k 12k
MMBtu
$7.22

731

Implemented Recommendations

3.5

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $45k 5.1k
MMBtu
3.3%
- Electrical $37k 495k
kWh
5.4%
- Natural Gas $3.2k -
MMBtu
-
Waste $0.8k
Productivity/Other $14k
TOTAL $61k
*May be negative reflecting an increased cost component required to save energy and costs overall