Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $698k | 120k |
MMBtu
|
$10.34 |
- Electrical | $465k | 7,673k |
kWh
|
$0.080 |
- Natural Gas | $75k | 17k |
MMBtu
|
$7.24 |
2,996
Recommendations
7.4
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $92k | 9.1k |
MMBtu
|
7.6% |
- Electrical | $66k | 890k |
kWh
|
11.6% |
- Natural Gas | $8.2k | - |
MMBtu
|
- |
Waste | $2.0k | |||
Productivity/Other | $42k | |||
TOTAL | $136k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
378
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $713k | 125k |
MMBtu
|
$10.21 |
- Electrical | $474k | 7,880k |
kWh
|
$0.078 |
- Natural Gas | $76k | 17k |
MMBtu
|
$7.13 |
1,280
Implemented Recommendations
3.4
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $39k | 4.2k |
MMBtu
|
3.3% |
- Electrical | $30k | 407k |
kWh
|
5.2% |
- Natural Gas | $2.7k | - |
MMBtu
|
- |
Waste | $0.6k | |||
Productivity/Other | $18k | |||
TOTAL | $57k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |