The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC | 2+ Digits Required | |
NAICS | Scale and balance manufacturing | |
SIC | 2+ Digits Required | |
3+ Characters Required for Products |
3
Matching Assessments
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $258k | 23k |
MMBtu
|
$10.25 |
- Electrical | $136k | 1,873k |
kWh
|
$0.071 |
- Natural Gas | $55k | 4.3k |
MMBtu
|
$7.09 |
27
Recommendations
9.0
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $47k | 2.3k |
MMBtu
|
9.9% |
- Electrical | $11k | 227k |
kWh
|
12.1% |
- Natural Gas | $22k | - |
MMBtu
|
- |
Waste | - | |||
Productivity/Other | $21k | |||
TOTAL | $68k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
3
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $258k | 23k |
MMBtu
|
$10.25 |
- Electrical | $136k | 1,873k |
kWh
|
$0.071 |
- Natural Gas | $55k | 4.3k |
MMBtu
|
$7.09 |
13
Implemented Recommendations
4.3
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $23k | 1.1k |
MMBtu
|
4.7% |
- Electrical | $5.4k | 107k |
kWh
|
5.7% |
- Natural Gas | $16k | - |
MMBtu
|
- |
Waste | - | |||
Productivity/Other | $1.3k | |||
TOTAL | $24k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |