ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS Conveyor and conveying equipment manufacturing
SIC 2+ Digits Required
3+ Characters Required for Products

22

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $257k 34k
MMBtu
$8.51
- Electrical $119k 2,302k
kWh
$0.056
- Natural Gas $65k 10k
MMBtu
$5.56

179

Recommendations

8.1

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $44k 3.8k
MMBtu
11.2%
- Electrical $20k 372k
kWh
16.2%
- Natural Gas $9.1k -
MMBtu
-
Waste $0.1k
Productivity/Other $11k
TOTAL $55k
*May be negative reflecting an increased cost component required to save energy and costs overall

19

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $256k 34k
MMBtu
$8.62
- Electrical $117k 2,362k
kWh
$0.054
- Natural Gas $65k 9.7k
MMBtu
$5.37

56

Implemented Recommendations

2.9

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $12k 1.1k
MMBtu
3.3%
- Electrical $5.6k 111k
kWh
4.7%
- Natural Gas $2.1k -
MMBtu
-
Waste $0.0k
Productivity/Other $3.2k
TOTAL $15k
*May be negative reflecting an increased cost component required to save energy and costs overall