ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS Other engine equipment manufacturing
SIC 2+ Digits Required
3+ Characters Required for Products

17

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $817k 117k
MMBtu
$8.08
- Electrical $495k 8,284k
kWh
$0.060
- Natural Gas $183k 31k
MMBtu
$6.62

134

Recommendations

7.9

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $108k 10k
MMBtu
9.0%
- Electrical $62k 1,021k
kWh
12.3%
- Natural Gas $36k -
MMBtu
-
Waste $9.4k
Productivity/Other $2.6k
TOTAL $120k
*May be negative reflecting an increased cost component required to save energy and costs overall

16

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $670k 97k
MMBtu
$8.14
- Electrical $425k 6,864k
kWh
$0.060
- Natural Gas $155k 26k
MMBtu
$6.70

57

Implemented Recommendations

3.6

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $35k 3.7k
MMBtu
3.8%
- Electrical $22k 360k
kWh
5.2%
- Natural Gas $7.7k -
MMBtu
-
Waste $0.0k
Productivity/Other $2.0k
TOTAL $37k
*May be negative reflecting an increased cost component required to save energy and costs overall