ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS Other industrial machinery manufacturing
SIC 2+ Digits Required
3+ Characters Required for Products

47

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $343k 46k
MMBtu
$9.82
- Electrical $179k 3,160k
kWh
$0.065
- Natural Gas $54k 6.6k
MMBtu
$6.71

394

Recommendations

8.4

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $63k 5.1k
MMBtu
11.1%
- Electrical $36k 499k
kWh
15.8%
- Natural Gas $10k -
MMBtu
-
Waste $2.2k
Productivity/Other $36k
TOTAL $102k
*May be negative reflecting an increased cost component required to save energy and costs overall

45

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $345k 47k
MMBtu
$9.81
- Electrical $180k 3,219k
kWh
$0.065
- Natural Gas $54k 6.5k
MMBtu
$6.72

176

Implemented Recommendations

3.9

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $29k 2.7k
MMBtu
5.7%
- Electrical $18k 262k
kWh
8.1%
- Natural Gas $1.6k -
MMBtu
-
Waste $0.0k
Productivity/Other $10k
TOTAL $39k
*May be negative reflecting an increased cost component required to save energy and costs overall