ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
NAICS 333132 Oil and gas field machinery and equipment manufacturing

48

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $535k 182k
MMBtu
$8.31
- Electrical $338k 16,491k
kWh
$0.064
- Natural Gas $83k 12k
MMBtu
$6.25

381

Recommendations

7.9

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $72k 7.2k
MMBtu
4.0%
- Electrical $48k 701k
kWh
4.3%
- Natural Gas $8.5k -
MMBtu
-
Waste $3.0k
Productivity/Other $19k
TOTAL $94k
*May be negative reflecting an increased cost component required to save energy and costs overall

46

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $544k 188k
MMBtu
$8.12
- Electrical $345k 17,112k
kWh
$0.063
- Natural Gas $84k 12k
MMBtu
$5.84

177

Implemented Recommendations

3.8

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $44k 4.4k
MMBtu
2.4%
- Electrical $30k 434k
kWh
2.5%
- Natural Gas $2.9k -
MMBtu
-
Waste $1.9k
Productivity/Other $10k
TOTAL $56k
*May be negative reflecting an increased cost component required to save energy and costs overall