The ITAC Statistics page displays the average assessment results for the selected criteria.
68
Matching Assessments
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $558k | 150k |
MMBtu
|
$9.15 |
- Electrical | $335k | 12,971k |
kWh
|
$0.47 |
- Natural Gas | $105k | 17k |
MMBtu
|
$6.36 |
555
Recommendations
8.2
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $75k | 6.7k |
MMBtu
|
4.5% |
- Electrical | $47k | 654k |
kWh
|
5.0% |
- Natural Gas | $14k | - |
MMBtu
|
- |
Waste | $2.3k | |||
Productivity/Other | $25k | |||
TOTAL | $103k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
65
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $566k | 156k |
MMBtu
|
$9.07 |
- Electrical | $341k | 13,437k |
kWh
|
$0.49 |
- Natural Gas | $107k | 17k |
MMBtu
|
$6.14 |
258
Implemented Recommendations
4.0
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $40k | 3.9k |
MMBtu
|
2.5% |
- Electrical | $26k | 384k |
kWh
|
2.9% |
- Natural Gas | $4.8k | - |
MMBtu
|
- |
Waste | $1.4k | |||
Productivity/Other | $11k | |||
TOTAL | $53k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |