Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $776k | 114k |
MMBtu
|
$7.85 |
- Electrical | $397k | 7,425k |
kWh
|
$0.062 |
- Natural Gas | $212k | 38k |
MMBtu
|
$5.91 |
322
Recommendations
7.9
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $91k | 8.9k |
MMBtu
|
7.8% |
- Electrical | $50k | 867k |
kWh
|
11.7% |
- Natural Gas | $24k | - |
MMBtu
|
- |
Waste | $2.5k | |||
Productivity/Other | $63k | |||
TOTAL | $156k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
39
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $795k | 115k |
MMBtu
|
$7.83 |
- Electrical | $406k | 7,667k |
kWh
|
$0.061 |
- Natural Gas | $215k | 36k |
MMBtu
|
$5.93 |
127
Implemented Recommendations
3.3
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $39k | 3.9k |
MMBtu
|
3.4% |
- Electrical | $19k | 384k |
kWh
|
5.0% |
- Natural Gas | $11k | - |
MMBtu
|
- |
Waste | $0.8k | |||
Productivity/Other | $48k | |||
TOTAL | $89k | |||