ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS Metal heat treating
SIC 2+ Digits Required
3+ Characters Required for Products

47

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $642k 112k
MMBtu
$8.65
- Electrical $231k 3,448k
kWh
$0.089
- Natural Gas $311k 77k
MMBtu
$8.25

341

Recommendations

7.3

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $86k 4.4k
MMBtu
3.9%
- Electrical $30k 429k
kWh
12.4%
- Natural Gas $41k -
MMBtu
-
Waste $5.9k
Productivity/Other $7.9k
TOTAL $100k
*May be negative reflecting an increased cost component required to save energy and costs overall

43

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $656k 118k
MMBtu
$7.75
- Electrical $233k 3,555k
kWh
$0.084
- Natural Gas $323k 82k
MMBtu
$7.34

142

Implemented Recommendations

3.3

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $29k 1.8k
MMBtu
1.5%
- Electrical $11k 171k
kWh
4.8%
- Natural Gas $12k -
MMBtu
-
Waste $6.4k
Productivity/Other $6.9k
TOTAL $42k
*May be negative reflecting an increased cost component required to save energy and costs overall