The ITAC Statistics page displays the average assessment results for the selected criteria.
247
Matching Assessments
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $631k | 93k |
MMBtu
|
$9.35 |
- Electrical | $237k | 4,056k |
kWh
|
$0.080 |
- Natural Gas | $278k | 50k |
MMBtu
|
$8.00 |
1,917
Recommendations
7.8
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $89k | 5.3k |
MMBtu
|
5.7% |
- Electrical | $38k | 514k |
kWh
|
12.7% |
- Natural Gas | $35k | - |
MMBtu
|
- |
Waste | $3.3k | |||
Productivity/Other | $11k | |||
TOTAL | $104k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
221
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $645k | 98k |
MMBtu
|
$8.92 |
- Electrical | $241k | 4,289k |
kWh
|
$0.077 |
- Natural Gas | $289k | 53k |
MMBtu
|
$7.83 |
830
Implemented Recommendations
3.8
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $30k | 2.3k |
MMBtu
|
2.4% |
- Electrical | $13k | 228k |
kWh
|
5.3% |
- Natural Gas | $12k | - |
MMBtu
|
- |
Waste | $1.9k | |||
Productivity/Other | $2.1k | |||
TOTAL | $34k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |