ITAC Statistics
ITAC logo
ITAC Statistics
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
The ITAC Statistics page displays the average assessment results for the selected criteria.
ARC 2+ Digits Required
NAICS Spring and wire product manufacturing
SIC 2+ Digits Required
3+ Characters Required for Products

58

Matching Assessments

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $605k 83k
MMBtu
$9.14
- Electrical $337k 5,433k
kWh
$0.070
- Natural Gas $157k 27k
MMBtu
$6.51

501

Recommendations

8.6

Recommendations Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $78k 7.2k
MMBtu
8.8%
- Electrical $42k 706k
kWh
13.0%
- Natural Gas $17k -
MMBtu
-
Waste $9.4k
Productivity/Other $21k
TOTAL $109k
*May be negative reflecting an increased cost component required to save energy and costs overall

55

with Implementation Data

Initial Plant Size Averages Costs Usage Unit Cost
All Energy $605k 84k
MMBtu
$9.07
- Electrical $338k 5,459k
kWh
$0.070
- Natural Gas $161k 28k
MMBtu
$6.29

217

Implemented Recommendations

3.9

Implemented Per Assessment

Average Rec'd Savings By Type* Cost Savings Usage Reduction % Usage
Reduction
All Energy $30k 2.9k
MMBtu
3.5%
- Electrical $17k 286k
kWh
5.2%
- Natural Gas $3.5k -
MMBtu
-
Waste $0.1k
Productivity/Other $0.8k
TOTAL $31k