The ITAC Statistics page displays the average assessment results for the selected criteria.
25
Matching Assessments
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $501k | 61k |
MMBtu
|
$9.85 |
- Electrical | $261k | 3,673k |
kWh
|
$0.075 |
- Natural Gas | $149k | 23k |
MMBtu
|
$7.35 |
205
Recommendations
8.2
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $103k | 6.5k |
MMBtu
|
10.6% |
- Electrical | $67k | 631k |
kWh
|
17.2% |
- Natural Gas | $9.2k | - |
MMBtu
|
- |
Waste | $0.2k | |||
Productivity/Other | $74k | |||
TOTAL | $177k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
23
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $533k | 66k |
MMBtu
|
$9.62 |
- Electrical | $277k | 3,927k |
kWh
|
$0.075 |
- Natural Gas | $160k | 24k |
MMBtu
|
$7.60 |
106
Implemented Recommendations
4.6
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $33k | 0.3k |
MMBtu
|
0.4% |
- Electrical | $8.3k | 26k |
kWh
|
0.7% |
- Natural Gas | $6.3k | - |
MMBtu
|
- |
Waste | $0.1k | |||
Productivity/Other | $75k | |||
TOTAL | $108k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |