The ITAC Statistics page displays the average assessment results for the selected criteria.
318
Matching Assessments
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $452k | 60k |
MMBtu
|
$10.56 |
- Electrical | $238k | 4,517k |
kWh
|
$0.094 |
- Natural Gas | $86k | 13k |
MMBtu
|
$6.58 |
2,347
Recommendations
7.4
Recommendations Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $58k | 5.3k |
MMBtu
|
8.8% |
- Electrical | $35k | 517k |
kWh
|
11.4% |
- Natural Gas | $9.5k | - |
MMBtu
|
- |
Waste | $1.8k | |||
Productivity/Other | $30k | |||
TOTAL | $90k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |
285
with Implementation Data
Initial Plant Size Averages | Costs | Usage | Unit Cost | |
---|---|---|---|---|
All Energy | $471k | 64k |
MMBtu
|
$10.16 |
- Electrical | $249k | 4,804k |
kWh
|
$0.093 |
- Natural Gas | $92k | 14k |
MMBtu
|
$6.46 |
918
Implemented Recommendations
3.2
Implemented Per Assessment
Average Recommended Rec'd Savings By Type* | Cost Savings | Usage Reduction | % Usage Reduction |
|
---|---|---|---|---|
All Energy | $19k | 2.1k |
MMBtu
|
3.2% |
- Electrical | $13k | 202k |
kWh
|
4.2% |
- Natural Gas | $2.3k | - |
MMBtu
|
- |
Waste | $0.2k | |||
Productivity/Other | $9.8k | |||
TOTAL | $29k | |||
*May be negative reflecting an increased cost component required to save energy and costs overall |